Summary
Staff provided a positive progress report on the Fenimore Woods stable restoration, noting construction is on track for a summer opening. The board also discussed the need for broader capital funding for other park maintenance needs, such as the Fenimore Woods pond.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 10, 2026.
Impact analysis
Funded through existing 2016 municipal bond proceeds and minor grants.
Township residents, park visitors, and youth camp participants.
Mentions & discussions (4)
Parks & Recreation Board - Sep 10, 2026
Radnor received a $700,000 state grant to help fund ongoing renovations at Fenimore Woods Park, including stable rehabilitation, path improvements, and potential pond restoration.
Board of Commissioners - May 18, 2026
The township reviewed major progress on the Fenimore Woods stable building renovation and park improvements. Commissioners approved a small electrical change order and amended a large contractor change order to separate out $350,000 in paving work so it can be competitively bid.
Parks & Recreation Board - Apr 9, 2026
Construction on the Fenimore Woods stable and pavilion is progressing steadily, with completion anticipated by early to mid-summer. The project remains in good financial standing thanks to grant funding and a settlement agreement.
Parks & Recreation Board - Feb 12, 2026
Staff provided a positive progress report on the Fenimore Woods stable restoration, noting construction is on track for a summer opening. The board also discussed the need for broader capital funding for other park maintenance needs, such as the Fenimore Woods pond.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Radnor
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.